📉 **Clouded Judgement: "Time to Power" — AI's Real Bottleneck Is Transmission**
Jamin Ball argues the gating constraint on the AI data center buildout is not power generation but transmission — moving electricity from generation sites through high-voltage lines and substations into data halls, a process PJM data shows takes roughly 3 years to reach an interconnection agreement and another 4 years to come online.

**Why it matters:** Investors evaluating AI infrastructure exposure should weight grid interconnection and transmission timelines, not just power generation capacity, when assessing how quickly compute buildout can actually scale.